Manufacture and installation of CIL tanks

Client:

Tietto

Project:

Manufacture and installation of CIL tanks

Location:

Abujar - Côte d'Ivoire

Scope:

  • Prefabrication of 800 metric tons of steel in the Friedlander workshop in Abidjan
  • Installation of 8 CIL tanks Ø 15.76 m x 17.5 m O/A, including surfacing work.
  • Installation of 12 treatment tanks
  • 8 months of work